Sign up for VMSPACE, Korea's best architecture online magazine.

Login Join


[10 Years of Design Competitions, 30 Public Architecture Selections] Dasan-myeon Town Hall Complex

DAUL ARCHITECTS & PLANNERS

written by
Sheen Dongjae
photographed by
Park Wansoon
materials provided by
DAUL ARCHITECTS & PLANNERS
edited by
Youn Yaelim, Kim Jia, Park Jiyoun, Ryu Jin
background

SPACE November 2023 (No. 672)  

 

10 years have passed since the design competition system was overhauled as a consequence of the Act On The Promotion Of Building Service Industry. As multiple adjustments and corrections have been made over time to the operation of design competitions, the system has given birth to numerous selections that populate our surroundings today. If these winning designs, which were born out of the creative struggles of individual designers in their respective times and places under the aegis of ¡®good public architecture¡¯, were to be assembled in a single space, what would stand out? SPACE have selected 30 distinguished examples of public architecture that have been recognised by the architectural scene over the past 10 years. We compared images of the winning designs and their results, and interviewed the architects. Our selection criteria was primarily based on being honoured with selection, but we also wanted to offer as diverse an outlook as possible according to type and year of competition, ordering institution, and use or function, to offer a wide spectrum of examples. When it came to public residences, we decided not to feature them in this article as they are a unique breed in terms of scale and programme. By reviewing all stages, from planning, examination, selection, and the post-construction phases, and after hearing from those responsible for them about the obstacles that they faced on their journey towards good public architecture, we hope that the testimonies of these people who witnessed the various aspects of the design competition system will give us a sense of continued direction as to where we should be heading in the next 10 years. 

 

©DAUL ARCHITECTS & PLANNERS

 

©Park Wansoon

 

Q1: From the design competition to construction, what was the main task when it came to the completion of your project? In which areas do you think your project did well, and what made this possible?

​A1: Goryeong-gun requested four facilities such as township office, library, health centre and culture centre under one single contract. Our design proposal deliberately removed any overlapping functions for economic reasons and a town-like urban space was proposed instead of the assumed single complex. Due to our previous experience of selection in Goryeong-gun¡¯s Daegaya Munhwanuri (2016) design competition, and as a result of the trust that we built with the client due to our high level of completion, allowed us to receive strong support from the client in terms of our new proposal and to finish it without much deviation from the original intentions. Although an external supervisor was appointed and a local contractor was selected for construction, they were all supportive of the designer¡¯s aims. We believe that our regular site visits and efforts were reflected in the level of final completion.

 

 

Q2: What suggestions would you make to improve the way design competitions are conducted in Korea?

A2: The problem of our design competition system can be divided into the selection process, the implementation of the design after the selection, and the construction process. Because the unfairness of the selection process is a pervasive problem concerning ethical conduct in the architectural field, a countrywide reformation toward civic mindedness would be its only solution. However, if the examination could proceed more transparently by disclosing the entire, and by using real names when voting, the reputation of the judges would be put under the spotlight and might bring about improvements in fairness and due process. In the execution stage, where more than half the labour concerns fitting the design plan within a limited budget, the realisation of a construction cost per area is urgently needed. Also the practice of preventing designers from designating specific products and specifications during the construction process is the major reason why the construction of public buildings is often left incomplete.

 

2015 general design competition

Architect  

DAUL ARCHITECTS & PLANNERS (Sheen Dongjae)

Location  

134-2, Sanggok-ri, Dasan-myeon, Goryeong-gun, Gyeongsangbuk-do

Programme  

office, education and research facility, neighbourhood living facility

Gross floor area  

5,208.22m©÷

Design cost  

budget – 631 million KRW / actual cost – 631 million KRW

Construction cost  

budget – 11.3 billion KRW / actual cost – 13.96 billion KRW

Competition year  

Nov. 2015

Completion year  

May 2018

Client  

Goryeong-gun

Prize  

Gyeongsangbuk-do Architecture Culture Award (2018), Korean Architecture Award (2019)​

You can see more information on the SPACE No. November (2023).

Architect

DAUL ARCHITECTS & PLANNERS (Sheen Dongjae)

Location

134-2, Sanggok-ri, Dasan-myeon, Goryeong-gun, Gyeo

Programme

office, education and research facility, neighbour

Gross floor area

5,208.22m©÷

Cost

budget – 11.3 billion KRW / actual cost R

Client

Goryeong-gun

Completion year

May 2018

Design cost

budget – 631 million KRW / actual cost ̵

Competition year

Nov. 2015


Sheen Dongjae

COMMENTS