Solution 1. Energy Performance: NAVER Data Center GAK Sejong Sever Building & Operation Building | Junglim Architecture

Junglim Architecture

photographed by
Yoon Joonhwan (unless otherwise indicated)
materials provided by
Junglim Architecture
edited by
Bang Yukyung, Lee Sowoon
background

SPACE May 2026 (No. 702) 

 

©Jang Mi 

 

Anodised panel façade installed on the roof of the Server Building ©Jang Mi​​

 

Perforated anodised panels ©NAVER Corporation (left), server racks in the server room. Screenshot form NAVER Corporation¡¯s YouTube (right) 

 

 

As Korea¡¯s largest hyperscale data centre, NAVER Data Center GAK Sejong offers an architectural solution to the challenges of massive power consumption and environmental impact. Given that data centers are highly sensitive to energy use, their architectural integrity depends heavily on technological and sustainable design capabilities. In designing the master plan, server buildings, and operations centre, Junglim Architecture integrated the site¡¯s topography, wind patterns, and existing ecosystem as core elements of the layout and landscaping. This approach minimised forest disturbance and established a plan for post-development ecological restoration, utilising native plant species in consideration of vegetation recovery. Plan and façade modules were engineered to minimise waste, and the massing of the server buildings was defined by the rack modules and their arrangement. Furthermore, the facility employs a natural cooling system using outdoor air to dissipate server heat, while repurposing waste heat and rainwater to promote energy efficiency and resource circularity.

 

 

 

 

Sketch of layout study in early stage

 

Currently programme diagram 

 

Computational fluid dynamics (CFD) simulation of outdoor air (OA) / exhaust air (EA) flow

 

 

 

 

Annual wind simulation for the Server Building layout 

 

 

©NAVER Corporation 

 

©Jang Mi 

 

 

 

 

 

You can see more information on the SPACE No. May (2026).

Architect

Junglim Architecture (Jeong Yongkyo, Lee Myungjin

Design team

Lee Myungjin, Ahn Jeongtaek, Choi Dongsik, Koh Ja

Location

Jiphyeon-dong, Sejong-si, Korea

Programme

broadcasting and communications facility (data c

Site area

293,697m©÷

Building area

32,703.27m©÷

Gross floor area

143,847.4m©÷

Building scope

B3, 4F

Parking

207

Height

35.75m

Building to land ratio

11.14%

Floor area ratio

18.59%

Structure

SRC, steel frame

Exterior finishing

exposed concrete, anodising aluminum panel

Interior finishing

exposed concrete, gypsum board

Structural engineer

Neo-Cross Structure Engineering Co., Ltd.

Mechanical engineer

HIMEC

Electrical engineer

Jung Woo Electric Design Center

Construction

Hyundai E&C

Design period

Phase 1 – Mar. 2020 – Aug. 2021 / Pha

Construction period

Phase 1 – May 2021 – Aug. 2023 / Phas

Client

NAVER Corporation

Landscape architect

Seo Ahn Total Landscape, Beyond Landscape Design

Fire protection engineer

Namdo TEC, Yungdo Engineers & Consultants

Façade consulting

FRONT Inc.